'7
I regret the delay which has occurred in
dealing with the Director of Colonial Audit's
minute of 21/11/33 on 13789/33. In that
minute he asks to see the approval of the
Secretary of State of excess expenditure during
1932 in connection with the following items of
the Shin Mun Valley Scheme (2nd Section)
(Preliminary Works
(
(Filters
(
(Gorge Dam
Excess Expenditure
$36.642.45
$11.213.89
$ 85.597.93✓
The same principles are involved in
regard to each of these items and it is proposed
to examine the first with a view to crystallising
those principles.
Preliminary Works
$36.642.45
At (14) on 92639/32 the Officer
Administering the Goverment forwarded a resolution
of the Legislature approving the expenditure of
$50.000 under this item. It was estimated that
this expenditure would be spread as follows:-
in 1931
in 1932
in 1933
$ 30.399.17
9.600.83
10.000.
$ 50.000.
This resolution did not apparently
receive the specific sanction of the Secretary of
State. -In the Estimates for 1933, however, in
(Appendix V(B)) this item of $50.000 appeared as
the Revised Estimated Cost of the "Preliminary
Works".
Those estimates were approved and
thereby the estimate of $50.000 for the "Preliminary
Works Shin Mun Valley Scheme (2nd Section) was
7
approved.
Subsequently
No comments yet.
Private notes are available after approval.